Delhaize | Ath

Client: Delhaize

Main contractor: Phenix group – Pepingen

The Delhaize branch in Ath, Hainaut, is being expanded. To supply the sprinkler system with water, a buffer tank of around 160 m³ is needed. Normally,

this solved by constructing a waterproof concrete tub. Here we work with two Tubao pipes of 2.30 m diameter, a total of 39 m long. These were installed with a

80 cm of cover. The pipes were joined together with a waterproof collar. They were then covered with a geogrid and backfilled with earth. This zone becomes a parking lot

so as the final layer asphalt was poured. With the Tubao steel pipes, the execution of the works was accelerated by 2 weeks.

Deschacht 17

Share this realization

Subscribe to our newsletter

Stay up to date with our latest news.

Related achievements

Deschacht and Tubao design fire water basins for new BMW dealership

View project

Brasserie du Bocq: a special sewerage system for an unusual project OK

View project

Flat roof with Starix Fleeceback EPDM

View project

DELTA-FLORAXX TOP protects basement against water I Lommel

View project

Water pumping: a technical challenge turned into a custom solution

View project

Subscribe to our newsletter!

Stay up to date with news and updates tailored to your field.