Early December 2025, circular 25/02 was published, providing further clarification on the application of the regional urban planning regulation on rainwater (GSV Hemelwater), particularly regarding requests for deviations for residential buildings. With this circular, Flanders primarily aims to offer greater clarity and a more consistent interpretation to permitting authorities and initiators.
At Deschacht, we closely follow these developments from our expertise in rainwater management and water infrastructure. In practice, legislation, technical feasibility, and sustainable water use are inextricably linked.
For whom?
Private domain and public domain that form part of a land subdivision
- From October 2, 2023
- Subject to licensingenvironmental permit application has been submitted as of 10/2/2023
- Not subject to a permit: projects of which the works have started from 10/2/2023
Public domain (public road, squares, parking lot, ...)
- Starting January 7, 2025
- Subject to licensingenvironmental permit application has been submitted as of this date
- Not subject to a permitCGPR
- Water retention remains the core ambition The objective of the Flemish rainwater policy is clear: to retain, reuse, and infiltrate rainwater locally to the maximum extent possible, regardless of the application or the nature of the environmental development. The regional ordinance forms the policy foundation for this and aims to guarantee qualitative water management in new developments. The circular explicitly confirms this starting point. It states that the GSV Hemelwater is in principle sufficient to achieve that objective and clarifies how the rules can be applied in a consistent and proportionate manner.
- A framework for interpretation, no additional tightening Circular 25/02 does not so much introduce new regulations as provide an interpretive framework. This framework is intended to prevent permit grantors from imposing stricter or additional requirements that are not explicitly included in the ordinance. In this way, Flanders aims to achieve greater legal certainty and uniformity among cities and municipalities. At the same time, the decision-making power remains with the permitting authority, which assesses each application within its local context and provides reasons for that decision. Deviations remain possible, provided they are well-founded and fit within the general objective of rainwater policy.
- Room for customization and technical creativity The circular emphasizes that within the GSV Rainwater guidelines, there remains room for customization and creative solutions. When traditional solutions are difficult to apply, alternatives—such as underground facilities, adjusted slope percentages, or specific designs in smaller gardens—can be considered, provided there is a sound justification.
- Practical applicability and administrative burden An important point of attention in the circular is avoiding unnecessary planning burdens during the design phase. The failure to provide additional technical information must not be a reason to declare a file inadmissible; further detailing often belongs in the implementation phase. This approach aligns with the evolution toward a modular environmental permit. In practice, however, it remains valuable when initiators provide sufficient technical substantiation and address additional questions from permitting authorities. This contributes to a high-quality assessment and prevents ambiguities from surfacing only during implementation or enforcement.
- Outlook on the future Although the circular focuses on clarity and flexibility within the existing framework, it remains relevant to continuously test rainwater management policies against future climate scenarios. More intense peak rainfall and longer periods of drought place new demands on design and implementation. This reflection is independent of the circular itself, but underscores the importance of technical expertise and thoughtful solutions that look beyond mere minimum compliance.
- Finally Circular 25/02 mainly aims to clarify, harmonize, and make practically applicable what is stipulated in the Flemish Regulation on the Discharge of Urban Wastewater and Rainwater (GSV Hemelwater). It confirms the basic principle of local water management, leaves room for customization, and keeps the decision-making authority with the permitting authority. At Deschacht, we see this as confirmation that sustainable rainwater management always requires a customized approach. With knowledge of regulations, insight into technical solutions, and attention to future challenges, we support designers, contractors, and public authorities in realizing robust and forward-looking water solutions.
Eleven solutions

Tubao winding tanks

HDPE pipes Weholite

Ribwall IT transport sewers

Buffer and infiltration crates