Drainix®: an infiltrating storage floor for Hubo Marche-en-Famenne

An infiltrating floor that combines storage with sustainable rainwater management

In Marche-en-Famenne, the Hubo store recently expanded its outdoor storage area. A seemingly simple project, but with a clear technical challenge: efficiently managing rainwater without overloading the existing sewage infrastructure. To tackle this, contractor Solidbeton, a specialist in polished concrete floors, proposed a pragmatic and high-performance solution: the Drainix® infiltrating floor, supplied by Deschacht.

An efficient technical choice

The affected area covers nearly 400 m² of flooring intended for the store's outdoor storage. The principle is clear: allow rainwater to infiltrate directly into the ground, as close as possible to the drop point. This is a solution particularly well-suited for large surfaces, where regulations and environmental requirements regarding water management are increasingly strict.

Drainix®: a floor designed for surface runoff infiltration

The Drainix® elements used on this site form a sustainable permeable surface, consisting of 15 cm thick PE Drainix® cellular panels, into which a reinforced concrete floor is poured on-site. This patented system combines the lightweight nature of a plastic structure with the mechanical strength of concrete, ensuring reliable durability, even under intensive traffic such as forklift use, once the surface is filled with crushed stone. This creates a high-performance infiltrating floor that promotes direct infiltration of rainwater into the subsoil.

With roughly 30% of openings, Drainix® easily exceeds the minimum legal threshold of 10% according to PTV 126 to be considered permeable. This generous margin guarantees an infiltration capacity that is significantly higher than the legal minimum.

Drainix® does not replace traditional sewage systems, but smartly complements them where infiltration is technically and economically feasible.

Professional execution by the contractor

On this construction site, the company handled the entire process: delivery of the concrete, pouring of the Drainix® floors, and finishing. Incidentally, this was not the first time. Following a previous successful project in Braine-l’Alleud (650 m²), the team was already completely familiar with the system. Result: smooth installation, with no need for specific on-site technical assistance.

Smooth partnership with Deschacht

Logistically, the project went smoothly. The Drainix® panels were delivered on time at a pre-agreed price. This is an essential point for a contractor who needs to plan their interventions precisely.

20260124 103111 scaled

Share this realization

Subscribe to our newsletter

Stay up to date with our latest news.

Related achievements

Pfizer chooses smart water solutions with Deschacht and Van Roey

View project

Sewerage for 3.5 ha site in Sint-Katelijne-Waver

View project

Water drainage | Lede

View project

Brasserie du Bocq: a special sewerage system for an unusual project OK

View project

Roof structure of new-build homes

View project

Subscribe to our newsletter!

Stay up to date with news and updates tailored to your field.