Client: Municipality of Houthulst
Main contractor: Timo-Tuin – Poperinge
Houthulst is getting a leisure campus. During the construction of the access road to the building, a problem arose. The road runs between two buildings and under a canopy. However, the canopy did not extend all the way to the buildings. There was no drainage system (80 meters) to collect rainwater.
An appropriate solution was needed because the height difference with the asphalt was not large enough to install a standard drainage channel. That would have stuck out above the asphalt. RECYFIX TOP X surface drainage from Hauraton was the best and fastest solution. The channel and the asphalt are now perfectly flush with each other. This is possible because the water is drained underground via an under-channel. RECYFIX TOP X is a lightweight, sturdy PE channel. In combination with the click system, this makes it very easy to install.